Colorado Springs Utilities projects

More than 1,500 linear feet of gas main infrastructure has been installed along Manitou Avenue and El Paso Boulevard for the Mesa to Manitou gas line replacement.

The gas line will be connected through Colorado Department of Transportation right of way and outside of a roadway. No impacts to the community will result from the connection.

Work continues on the gas line improvements on Park Avenue, Cañon Avenue and Lovers Lane. Some gas meters may also be replaced.

Construction activities are finished on Cañon Avenue, and have transitioned to Lovers Lane. Colorado Springs Utilities has been working in the intersection near Lovers Lane and Lafayette Road.

Work will continue down Lovers Lane to tie in with El Paso Boulevard gas lines.

Cañon Avenue will be paved fully once weather permits.